Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the the-events-calendar domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/html/eagle/public_html/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the complianz-gdpr domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/html/eagle/public_html/wp-includes/functions.php on line 6114
Central Park School, NYC – ERC

Central Park School, NYC

Central Park School, NY

The school board was facing a $500,000 to $600,000 cost to replace the entire HVAC system due to difficulty in maintaining and repairing the existing system. Contractors claimed that the obsolescence of parts and aging systems allowed no other option. Classroom temperatures ranged from 64 to 78 degrees.

Challenge

Contractors claimed that the obsolescence of parts and aging systems allowed no other option. Room temperatures ranged from 64 to 78 degrees.

Solution

Air Pro Experts proposed an all-inclusive, fixed-cost service agreement to assume the responsibility for preventative maintenance, repairs and equipment replacement for a fraction of the cost.

CLIENT:
Central Park School

CONTRACTOR:
Air Pro Experts

PROJECT DURATION:
January 2016 – May 2016

CONTRACT AMOUNT:
$28000.00